To enable funding to be in place for
preparatory work to continue on the White Rose Station scheme in
advance of the signing of a new Grant Agreement with the developer.
The station will be a new rail station with associated access
situated on the existing Leeds – Huddersfield Line alongside
the White Rose Office Park, Millshaw, Leeds, between Morley and
Cottingley on the Transpennine route.
Decision Maker: Director, Finance & Commercial Services
Decision published: 02/09/2021
Effective from: 27/08/2021
Decision:
To approve that
• The change request to re-profile the existing LPTIP
allocation on the scheme to use the unspent £741,000 from the
LPTIP Grant Agreement 1 approval to fund immediate works, required
to maintain the contractors programme and hit key pre booked
possession dates, is approved.
• The Combined Authority enters into a deed of variation to
the existing Grant Agreement with the developer.
Lead officer: Angela Taylor
To enable ongoing work to continue to complete
this scheme which will enhance the recently completed Scarborough
Bridge in York by making a number of improvements on the
Scarborough Bridge to Bootham Park route, aimed to make it easier
and help encourage greater use of the river crossing by
pedestrians, cyclists and the disabled
Decision Maker: Director, Finance & Commercial Services
Decision published: 02/09/2021
Effective from: 27/08/2021
Decision:
To approve that
• The change request to the TCF Early Wins York Scarborough
Bridge project to extend construction completion dates for 3
elements of the scheme with a final completion date of 31 March
2022 is approved.
• The Combined Authority enters into an addendum to the
existing funding agreement with City of York Council (CYC) for
expenditure of up to £280,000 from the Transforming Cities
Fund – Tranche 1 for York Scarborough Bridge scheme
Lead officer: Angela Taylor