To approve that
• The A61 South corridor scheme proceeds through decision
point 5 of the Combined Authority’s assurance process and
work commences on activity 6 (Delivery)
• Approval to the Combined Authority’s contribution of
£18.037 million funded through the Leeds Public Transport
Investment Programme is given towards a total project cost is
£18.247 million.
• The Combined Authority enters into an addendum to the
existing Funding Agreement with Leeds City Council for expenditure
up to £18.037 million from the Leeds Public Transport
Investment Programme fund.