A 61 South Corridor

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Decision:

To approve that
• The A61 South corridor scheme proceeds through decision point 5 of the Combined Authority’s assurance process and work commences on activity 6 (Delivery)
• Approval to the Combined Authority’s contribution of £18.037 million funded through the Leeds Public Transport Investment Programme is given towards a total project cost is £18.247 million.
• The Combined Authority enters into an addendum to the existing Funding Agreement with Leeds City Council for expenditure up to £18.037 million from the Leeds Public Transport Investment Programme fund.

Publication date: 17/02/2020

Date of decision: 14/02/2020