To approve that the first phases of the
following Corporate Technology Programme (CTP) work packages
proceeds through decision point 5 and work commences on activity 6
(delivery) :
o Z02 Internal Resource
o B02 Data Centre and Cloud Strategy
o B03 Active Directory
o B04 Network Infrastructure
o B05 Windows Server Upgrades
o D01 Mobile Access to Corporate Applications
o D02 End User Devices
o D04 Sharepoint online and Office 365
To give approval to the total value of the above work packages of
£2,183,996, taking the total approval for the CTP to
£3,090,996
To give approval to utilise the already approved £257,000 of
funding for the contingency/ start-up costs for the remaining
projects is given.