Decisions published

30/07/2021 - Corridor Improvement Programme: Calderdale - A646 - A6033 Corridor ref: 1085    Recommendations Approved

Approval for the scheme to progress through Activity 5 (Full Business Case plus finalised costs)

Decision Maker: Chief Executive

Decision published: 02/08/2021

Effective from: 10/08/2021

Decision:

To approve that

 

·        The Corridor Improvement Programme Calderdale A646-A6033 Corridor scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·        Approval to the total Combined Authority contribution of £3.988 million, to be funded through the West Yorkshire plus Transport Fund, is given. The total scheme value is £4.313 million, with a £0.325 million match contribution from Calderdale Council.

 

·        The Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for expenditure of up to £3.988 million from the West Yorkshire plus Transport Fund.

 

Lead officer: James Bennett


30/07/2021 - Corridor Improvement Programme: Calderdale - A58 - A672 Corridor ref: 1084    Recommendations Approved

Approval for the scheme to progress through Activity 5 (Full Business Case plus finalised costs)

Decision Maker: Chief Executive

Decision published: 02/08/2021

Effective from: 10/08/2021

Decision:

To approve that

 

·        The Corridor Improvement Programme A58/A672 scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·        Approval to the total scheme cost of £4.947 million, to be funded through the West Yorkshire plus Transport Fund, is given. 

 

·        The Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for total expenditure up to £4.947 million from the West Yorkshire plus Transport Fund.

 

Lead officer: James Bennett


29/07/2021 - Intra City Transport Settlements ref: 1082    Recommendations Approved

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved:

 

(a)      That the Combined Authority notes the Government’s proposals for the City Region Sustainable Transport Settlement and agrees to submit a CRSTS proposal for the 5-year period 2022/23 to 2026/27 to the Department for Transport, which is aligned to accelerating the delivery of the West Yorkshire Connectivity Infrastructure Plan.

(b)      That the Combined Authority agrees to delegate the decision on the detail of the final City Region Sustainable Transport Settlement submission to the Managing Director in consultation with the Mayor and Chair of Transport Committee.

(c)      That the Combined Authority notes the Government’s proposals for Active Travel Fund Local Authority Capital Funding for 2021/22 and agrees to submit a bid proposal and Expressions of Interests to the Department for Transport.

(d)      That the Combined Authority agrees to delegate the decision on the detail of the final bid proposal and Expression of Interests to the DfT Active Travel Fund Local Authority Capital Fund for 2021/22 to the Managing Director in consultation with the Mayor and Chair of the Transport Committee’s Active Travel Members Working Group.


29/07/2021 - Mayoral Pledge Funding ref: 1081    Recommendations Approved

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved:

 

(a)      That the Combined Authority indicatively approves funding from the Single Investment Fund to enable progress to be made in key priority areas, with full approval to spend being granted once the project has progressed through the assurance process in line with the Combined Authority’s Assurance Process. The indicative funding requested is:

·       £500k to support scheme development relating to business support.
 

·       £400k over three years to enable the recruitment of the Inclusivity Champion and further progress a pipeline of inclusive growth work.

(b)      That the Combined Authority notes that £190k from the £500k of SIF funding which was previously provisionally allocated to support scheme development relating to culture and creative industries and lead a creative new deal, is to be used to fund the Beyond Bronte’s programme, subject to Assurance Framework approvals.

(c)      That the Combined Authority delegates to the Finance, Resources and Corporate Committee, the approval for the programmes set out in the report to pass through Decision Point 2, totalling no more than £0.9m of funding from the Single Investment Fund.


29/07/2021 - Housing Pledge & Housing Revenue Fund Approval ref: 1071    Recommendations Approved

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved:

 

(a)      That the Combined Authority notes and endorses the approach to delivery of the Mayor’s housing pledge working closely with Partners, including Districts through their Directors of Development.

(b)      That following a recommendation from the Investment Committee, the Combined Authority approves:

 

(i)       That the Housing Revenue Fund programme proceeds through decision point 2 (strategic outline case) and decision point 4 (full business case) with Approval to Proceed to activity 5 (delivery).

(ii)      That approval to the remainder of the Combined Authority’s contribution of £2.95 million, funded from the West Yorkshire Devolution Deal, is given. The total scheme value if £3.2 million.

(iii)      That allocation of the £2.95 million of funding for the individual work packages is delegated to the Managing Director.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in appendix 1 of the submitted report.


29/07/2021 - Transforming Cities Fund: Halifax Bus Station ref: 1080    Recommendations Approved

Approval for the scheme to progress through Activity 5 (Full Business Case with finalised costs) and work commence on Activity 6 (Delivery).

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved: That in respect to Transforming Cities Fund Halifax Bus Station, the Combined Authority approves:

(i)       That the Transforming Cities Fund Halifax Bus Station scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).
 

(ii)      That approval to total scheme costs of £17.700 million is given, of which the Combined Authority to contribute £17.295 million from the Transforming Cities Fund and £0.405 million from the West Yorkshire plus Transport Fund.

(iii)      That the Combined Authority enters into a Memorandum of Understanding Agreement with Calderdale Council for expenditure up to £50,000 from the Transforming Cities Fund.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

Lead officer: Mark Auger


29/07/2021 - Place Narrative ref: 1070    Recommendations Approved

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved:

 

(a)      That the Place Narrative be approved and its positioning as part of the Strategic Economic Framework be endorsed.

(b)      That approval of future updates of the Place Narrative be delegated to the Place, Regeneration and Housing Committee. 


29/07/2021 - Brownfield Housing Fund Programme ref: 1073    Recommendations Approved

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved:

(a)      That the Combined Authority notes the work undertaken so far on the Brownfield Housing Fund Programme.

(b)      That the Combined Authority sequencing of Waves and associated projects in Exempt Appendix 1 be endorsed.

(c)      That in light of the proposed changes to Committees, future project approvals are made in accordance with the assurance pathway and approval route outlined and approved by the Combined Authority in September 2020, including at the next decision point through delegation to the Place, Regeneration and Housing Committee and at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team.

(d)      That to ensure the programme progresses at pace, to delegate to the Director of Delivery, in consultation with the Portfolio Holder for Place, Regeneration and Housing:

(i)       The review and transfer of projects between the project prioritisation ‘Waves’ detailed in Exempt Appendix 1.

(ii)      The acceptance of new projects on to the programme.

(iii)      The transfer of projects which place greater risk on the programme back to the Strategic Housing pipeline for consideration as part of future investment programmes.

 


29/07/2021 - Capital Spending & Project Approvals ref: 1074    Recommendations Approved

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved:

(a)      That in respect of the Clifton (Calderdale) Enterprise Zone Business Rates Receipt, the Combined Authority approves that, subject to the conditions in the submitted report, Calderdale Council retains future business rates income generated from the Clifton Enterprise Zone (up to March 2042).

(b)      That in respect of the British Library for the North (Temple Works), the Combined Authority approves:

 

(i)       That the British Library for the North (Temple Works) scheme proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case).

(ii)      That an indicative approval of £25 million (to be funded through the Combined Authority’s devolution deal) is given. The total forecast scheme value is £69.810 million.

(iii)      That approval of £5.35 million development costs to progress the scheme to decision point 3 (outline business case) be given.

(iv)     That the Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £5 million from the Combined Authority’s devolution deal.

(v)      That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

(c)      That in respect of the TCF Network Navigation, the Combined Authority approves:

(i)       That the TCF Network Navigation project proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case)

(ii)      That an indicative approval to the total project value of £15.500 million, comprising of £15.200 million from the Transforming Cities Fund, and £0.300 million from Local Transport Plan Integrated Transport Block, is given.

(iii)      That development costs of £0.200 million are approved to progress the scheme to decision point 4 (full business case) taking the total scheme approval to £0.360 million.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

(d)      That in respect of the CityConnect Phase 3 Canals - Leeds Liverpool Shipley, the Combined Authority approves, subject to the conditions set by PAT stated in the submitted report:

(i)       That the CityConnect Phase 3 Canals - Leeds Liverpool Shipley scheme proceeds through decision point 4 (full business case) and work commences on activity 5 (Delivery).

(ii)      That approval to the Combined Authority’s contribution of £1.981 million which will be funded from West Yorkshire plus Transport Fund (£1.057 million), Getting Building Fund (£0.500 million) and £0.424 million yet to be secured is given. The total scheme value is £1.981 million.

(iii)      That the Combined Authority enters into an addendum to the existing funding agreement with the Canal and River Trust for expenditure of up to £1.981 million.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

(e)      That in respect of the CityConnect Phase 3 Canals - Huddersfield Narrow Canal (HNC) Phase 2, the Combined Authority approves, subject to the conditions set by PAT stated in the submitted report:

 

(i)       That the CityConnect Phase 3 Canals – Huddersfield Narrow Canal Phase 2 scheme proceeds through Decision Point 4 (full business case) and work commences on Activity 5 (Delivery).

(ii)      That approval to the Combined Authority’s contribution of £1.371 million (which will be funded through £0.643 million from the West Yorkshire plus Transport Fund and £0.728 million from the Active Travel Fund) is given. The total scheme value is £1.371 million.

(iii)      That the Combined Authority enters into an addendum to the existing funding agreement with the Canal and River Trust for expenditure of up to £0.643 million from the West Yorkshire plus Transport Fund.

(iv)     That the Combined Authority enters into an addendum to the existing funding letter with Kirklees Council for expenditure of up to £0.728 million from the Active Travel Fund.

(v)      That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.
 

(f)       That in respect to Transforming Cities Fund Halifax Bus Station, the Combined Authority approves:

(i)       That the Transforming Cities Fund Halifax Bus Station scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).
 

(ii)      That approval to total scheme costs of £17.700 million is given, of which the Combined Authority to contribute £17.295 million from the Transforming Cities Fund and £0.405 million from the West Yorkshire plus Transport Fund.

(iii)      That the Combined Authority enters into a Memorandum of Understanding Agreement with Calderdale Council for expenditure up to £50,000 from the Transforming Cities Fund.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.


29/07/2021 - Enterprise Zone Programme, Clifton, Calderdale ref: 1075    Recommendations Approved

The Combined Authority receives 100% of the Business Rates generated within the EZ sites for a period of 25 years from date of designation (up to March 2042 for phase 2 sites, which includes Clifton). Calderdale Council have asked the Combined Authority, as accountable body for the LEP, to consider the passporting of future business rates from the Clifton site to the Council to support prudential borrowing for capital required to deliver the full scheme of enabling works.

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved: That in respect of the Clifton (Calderdale) Enterprise Zone Business Rates Receipt, the Combined Authority approves that, subject to the conditions in the submitted report, Calderdale Council retains future business rates income generated from the Clifton Enterprise Zone (up to March 2042).

Lead officer: Jess McNeill


29/07/2021 - Transforming Cities Fund: Network Navigation - West Yorkshire ref: 1077    Recommendations Approved

Approval for the scheme to progress through Activity 3 (Outline Business Case)

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved: That in respect of the TCF Network Navigation, the Combined Authority approves:

(i)       That the TCF Network Navigation project proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case).

(ii)      That an indicative approval to the total project value of £15.500 million, comprising of £15.200 million from the Transforming Cities Fund, and £0.300 million from Local Transport Plan Integrated Transport Block, is given.

(iii)      That development costs of £0.200 million are approved to progress the scheme to decision point 4 (full business case) taking the total scheme approval to £0.360 million.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

Lead officer: Fiona Limb


29/07/2021 - Housing Revenue Fund ref: 1072    Information Only

Approval for the scheme to progress through Activity 2 (Strategic Outline Case).

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved: That following a recommendation from the Investment Committee, the Combined Authority approves:

 

(i)       That the Housing Revenue Fund programme proceeds through decision point 2 (strategic outline case) and decision point 4 (full business case) with Approval to Proceed to activity 5 (delivery).

(ii)      That approval to the remainder of the Combined Authority’s contribution of £2.95 million, funded from the West Yorkshire Devolution Deal, is given. The total scheme value if £3.2 million.

(iii)      That allocation of the £2.95 million of funding for the individual work packages is delegated to the Managing Director.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in appendix 1 of the submitted report.

Lead officer: Rebecca Greenwood


29/07/2021 - CityConnect Phase 3 Canals - Huddersfield Narrow Canal Phase 2 ref: 1079    Recommendations Approved

Approval for the scheme to progress through Activity 5 (Full Business Case with finalised costs) and work commence on Activity 6 (Delivery).

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved: That in respect of the CityConnect Phase 3 Canals - Huddersfield Narrow Canal (HNC) Phase 2, the Combined Authority approves, subject to the conditions set by PAT stated in the submitted report:

 

(i)         That the CityConnect Phase 3 Canals – Huddersfield Narrow Canal Phase 2 scheme proceeds through Decision Point 4 (full business case) and work commences on Activity 5 (Delivery).

(ii)        That approval to the Combined Authority’s contribution of £1.371 million (which will be funded through £0.643 million from the West Yorkshire plus Transport Fund and £0.728 million from the Active Travel Fund) is given. The total scheme value is £1.371 million.

(iii)       That the Combined Authority enters into an addendum to the existing funding agreement with the Canal and River Trust for expenditure of up to £0.643 million from the West Yorkshire plus Transport Fund.

(iv)       That the Combined Authority enters into an addendum to the existing funding letter with Kirklees Council for expenditure of up to £0.728 million from the Active Travel Fund.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

Lead officer: Robert Griffiths


29/07/2021 - CityConnect Phase 3 Canals - Leeds Liverpool Shipley ref: 1078    Recommendations Approved

Approval for the scheme to progress through Activity 5 (Full Business Case with Finalised Costs).

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved: That in respect of the CityConnect Phase 3 Canals - Leeds Liverpool Shipley, the Combined Authority approves, subject to the conditions set by PAT stated in the submitted report:

(i)       That the CityConnect Phase 3 Canals - Leeds Liverpool Shipley scheme proceeds through decision point 4 (full business case) and work commences on activity 5 (Delivery).

(ii)      That approval to the Combined Authority’s contribution of £1.981 million which will be funded from West Yorkshire plus Transport Fund (£1.057 million), Getting Building Fund (£0.500 million) and £0.424 million yet to be secured is given. The total scheme value is £1.981 million.

(iii)      That the Combined Authority enters into an addendum to the existing funding agreement with the Canal and River Trust for expenditure of up to £1.981 million.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

Lead officer: Robert Griffiths


29/07/2021 - British Library for the North ref: 1076    Recommendations Approved

Approval for the scheme to progress through Activity 2 (Strategic Outline Case)

Decision Maker: West Yorkshire Combined Authority

Made at meeting: 29/07/2021 - West Yorkshire Combined Authority

Decision published: 29/07/2021

Effective from: 06/08/2021

Decision:

Resolved: That in respect of the British Library for the North (Temple Works), the Combined Authority approves:

 

(i)       That the British Library for the North (Temple Works) scheme proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case).

(ii)      That an indicative approval of £25 million (to be funded through the Combined Authority’s devolution deal) is given. The total forecast scheme value is £69.810 million.

(iii)      That approval of £5.35 million development costs to progress the scheme to decision point 3 (outline business case).

(iv)     That the Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £5 million from the Combined Authority’s devolution deal.

(v)      That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.

Lead officer: Elizabeth Courtney


16/07/2021 - One Public Estate – Land Release Fund Change Request ref: 1069    Recommendations Approved

To enable delivery to continue on LRF schemes in Wakefield and Craven contributing to the completion of 74 housing units across the LRF programme.

Decision Maker: Chief Executive

Decision published: 21/07/2021

Effective from: 16/07/2021

Decision:

To approve that:
i. The change request to the Land Release Fund (LRF) programme is approved. This confirms that the overall LRF programme cost is £475,875.
ii. The delivery timeframe for Craven’s Airedale Avenue and Wakefield’s Langthwaite Lane projects within the LRF programme is extended to March 2022.
iii. The Combined Authority enters into a funding agreement with Wakefield Council for expenditure of up to £19,375 from the Land Release Fund.
iv. The Combined Authority extends the funding agreement with Craven District Council for the Airedale Avenue site until the end of March 2022.

Lead officer: Ben Still


20/07/2021 - Lifetime Skills Guarantee: Level 3 delegated funding ref: 1068    Recommendations Approved

To allocate delegated funding from Department for Education to support the new Lifetime Skills Guarantee to Grant providers route 1: Level 3 Adult Offer to the total value of £4,622,770 for delivery from 1 August 2021.

Decision Maker: Chief Executive

Decision published: 20/07/2021

Effective from: 30/07/2021

Decision:

To:

 

(i)   approve the allocations for the Lifetime Skills Level 3 Guarantee allocations,

(ii)   enter into contracts with the suppliers listed in the report submitted to the decision maker.

 

Lead officer: Catherine Lunn


12/07/2021 - Transforming Cities Fund - Kirklees Early Walking and Cycling Gateways – Dewsbury Rail Station Access and Huddersfield Better Connected Stations ref: 1067    Recommendations Approved

To enable the completion of the schemes to provide walking and cycling facility improvements at Dewsbury and Huddersfield rail stations alongside improvements to walking and cycling access routes to the stations.

Decision Maker: Chief Executive

Decision published: 19/07/2021

Effective from: 12/07/2021

Decision:

To approve that:
i.The change request to the TCF Kirklees Early Walking and Cycling Gateways – Dewsbury Rail Station Access and Huddersfield Better Connected Stations projects, to change the completion dates and funding profile, is approved.
ii.The Combined Authority enters into an addendum to the existing funding agreement with Kirklees Council for expenditure of up to £1.735 million from the Transforming Cities Fund – Tranche 1/Early Gateways for the Huddersfield Better Connected Stations project.
iii.The Combined Authority enters into a funding agreement with Kirklees Council for expenditure up to £0.160 million from the Transforming Cities Fund – Tranche 1/Early Gateways for the Dewsbury Rail Station Access project.

Lead officer: Ben Still