To approve that
· The GBF Grey to Green (Sovereign Square Footbridge and Crown Point Road elements) scheme proceeds through Full Business Case with Finalised Costs and work commences on activity 5 (Delivery).
· Approval to the Combined Authority’s contribution of £3,854,000 (which will be funded from the Getting Building Fund) is given, which brings the total approval to £8,600,000. The total scheme value is £13.117 million.
· The Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £8,600,000 from the Getting Building Fund.