To approve that
• The change request to the TCF Early Wins York Scarborough
Bridge project to extend construction completion dates for 3
elements of the scheme with a final completion date of 31 March
2022 is approved.
• The Combined Authority enters into an addendum to the
existing funding agreement with City of York Council (CYC) for
expenditure of up to £280,000 from the Transforming Cities
Fund – Tranche 1 for York Scarborough Bridge scheme