To approve that:
· The Corridor Improvement Programme – Bradford – A6177 Great Horton Road – Horton Grange Road scheme proceeds through decision point 4 and work commences on activity 5 (Full business case with finalised costs).
· An indicative approval to the total scheme value of £4.457 million is given from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).
· Additional development costs of £0.140 million are approved in order to progress the scheme to decision point 5 (Full business case with finalised costs) taking the total scheme approval to £0.949 million.
· The Combined Authority enters into a Funding Agreement with Bradford Council for expenditure of up to £0.949 million from the West Yorkshire plus Transport Fund.