Corridor Improvement Programme: Bradford - A6177 Great Horton Road - Horton Grange Road

13/04/2021 - Corridor Improvement Programme: Bradford - A6177 Great Horton Road - Horton Grange Road

To approve that:         

·       The Corridor Improvement Programme – Bradford – A6177 Great Horton Road – Horton Grange Road scheme proceeds through decision point 4 and work commences on activity 5 (Full business case with finalised costs).

 

·       An indicative approval to the total scheme value of £4.457 million is given from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

 

·       Additional development costs of £0.140 million are approved in order to progress the scheme to decision point 5 (Full business case with finalised costs) taking the total scheme approval to £0.949 million.

 

·       The Combined Authority enters into a Funding Agreement with Bradford Council for expenditure of up to £0.949 million from the West Yorkshire plus Transport Fund.