A629 Phase 1b

31/03/2021 - A629 Phase 1b

To approve that
•The A629 Phase 1b (part 1) scheme proceeds through decision point 5 of the Combined Authority’s assurance process and work commences on activity 6 (delivery).
•Approval to the A629 Phase 1b (part 1) scheme value of £5.810 million is given from the West Yorkshire plus Transport Fund (WY+TF), taking the total approval from the WY+TF to £11.48 million.
•An indicative approval to the A629 Phase 1b (part 2) scheme value of £15.32 million is given from the West Yorkshire plus Transport Fund (WY+TF), with full approval to spend being granted once the scheme has fully progressed through decision point 5 (Full business case with finalised costs) of the assurance process.
•The Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for expenditure of up to £11.48 million from the WY+TF fund.