Resolved: In respect of TCF: Dewsbury–Batley–Tingley Sustainable Travel Corridor –
That following a recommendation from the Investment Committee, the Combined Authority approves:
(i) That the Dewsbury–Batley–Tingley Sustainable Travel Corridor package project proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case)
(ii) That an indicative approval to the total project value of £6 million is granted from the Transforming Cities Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the package remaining within the tolerances outlined in the report.