Issue - decisions

Bus Priority Corridors - A61 South

27/04/2020 - Bus Priority Corridors - A61 South

  To approve that

                The A61 South corridor scheme proceeds through decision point 5 of the Combined Authority’s assurance process and work commences on activity 6 (Delivery)

                Approval to the Combined Authority’s contribution of £18.037 million funded through the Leeds Public Transport Investment Programme is given towards a total project cost is £18.247 million.

                The Combined Authority enters into an addendum to the existing Funding Agreement with Leeds City Council for expenditure up to £18.037 million from the Leeds Public Transport Investment Programme fund.