Resolved: That following a recommendation from the Investment Committee, the Combined Authority approves:

(a)       That the Ultra-Low Emission Bus (ULEB) scheme proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs)

(b)       That an indicative approval is given to the Combined Authority’s contribution of £1.650 million (which will be funded through £1.033 million from Leeds Public Transport Investment Programme (LPTIP) and £617,000 from the DfT ULEB scheme fund), with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total project value of £2.7 million.

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.