Halifax Station Gateway (Transport Scheme)

15/07/2019 - Halifax Station Gateway (Transport Scheme)

(i)        That in respect of Halifax Station Gateway the Investment Committee resolved:

(a)       That the change request to the Halifax Station Gateway project to provide £247,336 of additional development funds be approved.

(b)       That the timeframe extension outlined in this report be approved.

(c)       That the Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for additional expenditure of £247,336 taking the total approval up to £1.355 million from the West Yorkshire plus Transport Fund.

(d)       That future approvals are made in accordance with the approval pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.