Resolved: That in respect of West Yorkshire Combined Authority Head Office Accommodation Project Investment Committee approves that:
(a) The West Yorkshire Combined Authority Head Office Accommodation
project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).
(b) An indicative approval to the total project cost of £6.847 million is given.
This will be funded entirely by the Combined Authority (from the approved
budget for Corporate Projects), with full approval to spend being granted
once the scheme has progressed through the assurance process to
decision point 5 (full business case with finalised costs).
(c) Future approvals are made in accordance with the assurance pathway
and approval route set out in the submitted report following a
recommendation by the Combined Authority’s Programme Appraisal
Team. This will be subject to the scheme remaining within the tolerances
outlined in the report.