Resolved - That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the A6177 Great Horton Road / Horton Grange Road scheme proceeds through decision point 3 and work commences on activity 4 (full business case).

(ii)        That an indicative approval to the total project value of £4.205 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That additional development costs of £584,007 are approved in order to progress the scheme to full business case with finalised costs (decision point 5), taking the total project approval to £809,007.

(iv)       That the Combined Authority enters in to funding agreement with Bradford Council for expenditure of up to £809,007 from the West Yorkshire plus Transport Fund.

(v)        That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report, including at decision points 4 and 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.