Resolved:
In respect of York Outer Ring Road Phase 2 (Monks Cross) –
That following a recommendation from the Investment Committee, the Combined Authority approves:
(i) That the York Outer Ring Road Phase 2 project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs)
(ii) That an indicative approval to Phase 2 to the value of £3.585 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.