Elland Road Park and Ride (Phase 3)

14/12/2018 - Elland Road Park and Ride (Phase 3)

Resolved:

In respect of Elland Road Park and Ride Phase 3 –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Elland Road Park and Ride Phase 3 project proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs).

(ii)        That an indicative approval to the total project value of £5.75 million is given to be funded from the Combined Authority from the Leeds Public Transport Investment Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That further development costs of £165,000 are approved in order to progress the scheme to decision point 5 (full business case with finalised costs) taking the total development cost expenditure approval to £410,000.

(iv)       That the Combined Authority enters into an addendum to the existing Funding Agreement with Leeds City Council to increase by £165,000 from the Leeds Public Transport Investment Fund for expenditure of up to £410,000.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.