26/09/2018 - A629 Phase 2, Calderdale

To approve the change request to the A629 phase 2 scheme to approve development costs of £366,415 for the bus station component, taking the total scheme development costs to £2,981,415.

To approve that the Combined Authority enters into an amendment to the Funding Agreement with Calderdale Council for additional expenditure of up to £366,415 from the West Yorkshire-plus Transport Fund.