Issue - decisions

Bradford Interchange Phase 1

01/02/2018 - Bradford Interchange Phase 1 (Decision Point 2 Case Paper)

Resolved: In respect of Bradford Interchange Phase 1 (Decision Point 2 Case Paper)

 

That following a recommendation from the Investment Committee, WYCA approves:

 

(a)       That the Bradford Interchange Phase 1 project proceeds through Decision Point 2 and work commences on Activity 3 (Outline Business Case) of the Assurance process.

 

(b)       That an indicative approval to the total project value of up to £5.65m is given to be funded from the West Yorkshire plus Transport Fund, with Full Approval to spend being granted once the scheme has progressed through the Assurance Process to Decision Point 5 (FBC with Finalised Costs).

 

(c)        That further development costs of up to £0.100m are approved in order to progress the scheme to Decision Point 3 (Outline Business Case) taking the total project approval to £0.180m, and that WYCA enter into an addendum to the existing funding agreement with City of Bradford Metropolitan District Council for total expenditure of up to £0.180m from the West Yorkshire plus Transport Fund.

 

(d)       That future approvals are made in accordance with the Approval Pathway and Approval Route set out in this Case Paper. This will be subject to the scheme remaining within the tolerances outlined in the Case Paper.