Rail Park & Ride Programme – Steeton & Silsden Station

21/06/2022 - Rail Park & Ride Programme – Steeton & Silsden Station

• Approval of the change request for the Steeton and Silsden rail car park extension scheme to increase the scheme allocation by £175,000, from £4,630,800 to £4,805,800 is approved. The additional funding is to be re-allocated from within the Rail Park and Ride programme allocation of £31,500,000

• The Combined Authority enters into a variation to an existing asset protection agreement with Network Rail for additional costs of up to £175,000, from £61,100 to up to £236,100.