Resolved: The Combined Authority approves that:
a)
the CIP - A629(N) – Ogden to Orange Street
Roundabout scheme proceeds through decision 3 (outline business
case) and work commences on activity 4 (full business
case).
b)
an indicative approval to the Combined
Authority’s contribution of £6,100,000 is given. The
total scheme value is £7,010,000.
c)
additional development costs of £1,180,000 are
approved in order to progress the scheme to decision point 4 (full
business case), taking the total scheme approval to
£1,810,000.
d)
the Combined Authority enters into a funding
agreement with Calderdale Metropolitan Borough Council for
expenditure of up to £1,810,000.
e) future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.