Issue - decisions

Corridor Improvement Programme - Calderdale - A629 North – Orange Street

03/02/2022 - Capital Spending and Project Approvals

Resolved: The Combined Authority approves that:

 

a)    the CIP - A629(N) – Ogden to Orange Street Roundabout scheme proceeds through decision 3 (outline business case) and work commences on activity 4 (full business case).

b)    an indicative approval to the Combined Authority’s contribution of £6,100,000 is given. The total scheme value is £7,010,000.

c)    additional development costs of £1,180,000 are approved in order to progress the scheme to decision point 4 (full business case), taking the total scheme approval to £1,810,000.

d)    the Combined Authority enters into a funding agreement with Calderdale Metropolitan Borough Council for expenditure of up to £1,810,000.

e)    future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.