(Lead Member: The Mayor, Director: Melanie Corcoran)
Decision:
Resolved:
a)
That in respect of CRSTS
Capacity Funding, the Combined Authority approves that:
i)
the CRSTS Capacity Fund scheme proceeds through
decision point 2 to 4 (business justification) and work commences
on activity 5 (delivery).
ii)
indicative approval is given to the Combined
Authority’s contribution of £7,400,000. The total
scheme value is £7,400,000.
iii)
approval to £2,756,411 for tranche 2 (of 3) is
given, allocated as detailed in Appendix 2 of the submitted report,
bringing the total approval to £5,756,411.
iv)
the Combined Authority enters
into a Funding Agreement with each of the councils for expenditure
as detailed in Appendix 2 of the submitted report.
v)
changes to allocations in iii)
and iv) above are delegated to the Senior Responsible Officer
(Interim Director of Policy and Development) of the CRSTS
programme.
vi)
future approvals are made in
accordance with the assurance pathway and approval route outlined
in the submitted report and where required, any change requests are
delegated to the Transport Committee. This will be subject to the
scheme remaining within the tolerances outlined in the submitted
report.
b)
That in respect of Gainshare
Capacity Funding, the Combined Authority approves that:
i)
the Gainshare Capacity Funding
scheme proceeds through decision point 2 to 4 (business
justification) and work commences on activity 5
(delivery).
ii)
approval to the total scheme
value of £11,400,000 is given, allocated as detailed in
Appendix 4 of the submitted report.
iii)
the Combined Authority enters into a Funding
Agreement with each of the councils for expenditure of up to
£1,890,000.
iv)
future approvals are made in accordance with the
assurance pathway and approval route outlined in the submitted
report and where required, any change requests are delegated to the
Finance, Resources and Corporate Committee. This will be subject to
the scheme remaining within the tolerances outlined in the
submitted report.
c)
That in respect of the CRSTS
Programme, the Combined Authority approves that, subject to the
successful outcome of the bid to DfT:
i)
the City Region Sustainable
Transport Settlement (CRSTS) programme proceeds through decision
point 2 (strategic outline case) and work commences on development
of the relevant business case for each individual scheme.
ii)
an indicative approval to the total programme value
of £830,000,000 is given. The total programme cost is
£1,231,994,853.
iii) approval of development and delivery costs of up to £63,455,916 for business case development and programme management costs is given as follows:
· Up to £30,311,916 for monitoring and evaluation, communications, consultation and engagement and Combined Authority programme management.
· Development costs of up to £3,000,000 to enable delivery partners to develop scheme business cases.
· Delivery and development costs of up to £30,144,000 for the development of strategic outline cases and quarter 1 and quarter 2 costs for the Highways Asset Management, Network Management and Safer Roads programme.
iv)
approval is given for the delegation of authority to
the Combined Authority’s Director of Delivery, following a
recommendation from the Programme Appraisal Team, to approve
requests for business case development costs, in accordance with
the Assurance Framework.
v)
approval is given for the delegation of authority to
the Combined Authority’s Managing Director, following a
recommendation from the Programme Appraisal Team, to approve the
behaviour change programme proceeding into delivery in accordance
with the Assurance Framework from the indicative allocation of
£10,550,000.
vi)
in order to
ensure that schemes can be delivered within the
tight timescales, the Combined Authority delegates authority to the
Managing Director to amend the approval and allocation of CRSTS if
the DfT award differs from £830,000,000, or if further
changes to individual allocations is required, as a result of
changes to the programme and approaches to delivery.
vii) The Combined Authority enters into Funding Agreements with partners councils for expenditure, for the Highways Asset Management, Network Management and Safer Roads programme, up to the amounts shown below:
· Bradford £6,486,308
· Calderdale £3,846,476
· Kirklees £6,161,288
· Leeds £9,281,288
· Wakefield £4,368,640
viii) Future
approvals are made in accordance with the assurance pathway and
approval route outlined in the submitted report and any change
requests are delegated to the Transport Committee, which will be
subject to the scheme remaining within the tolerances outlined in
the submitted report.
d)
That in respect of Transformational - West Yorkshire
Mass Transit, the Combined Authority, subject to the conditions set
by Programme Appraisal Team:
i)
approves the West Yorkshire Mass Transit Programme
proceeds through Decision Point 2 and work commences on Activity 3
(outline business case) for the Programme Integration Business Case
and on Activity 2 (strategic outline case) for the four phased
corridor projects within the programme.
ii)
endorses the proposed Mass Transit Programme scope,
ambition and network and the approach to phase development of
projects within the overall programme.
iii)
notes that future assurance of any Mass Transit
business case will be “called in” by central
government.
iv)
indicatively approves £200,000,000 (subject to
grant determination letter from government) to develop the West
Yorkshire Mass Transit programme. Total scheme value is to be
determined.
v)
approves development costs of £31,887,500
in order to progress each of the four
phased project business cases to Decision Point 2 (strategic
outline case), and the Programme Integration Business Case to
Decision Point 3 (subject to Grant Determination letter from
Government). This would take the total project approval to
£33,928,500.
vi)
approves that future
approvals are made in accordance with the Approval Pathways
and Approval Routes outlined in the submitted report and where
required any change requests are delegated to the Transport
Committee. This will be subject to the scheme remaining within the
tolerances outlined in the submitted report.
Conditions for approval of Activity 2 (SOC) for the
Programme Integration Business Case:
vii)
Provide full details of the optioneering and options
appraisal methodology, including clearly defined critical success
factor development and use, criteria on technology and route
options, low-cost options considered and first phase option
criteria and include how approval was managed at each
stage.
viii) Provide
information on cost benchmarking exercise.
ix)
Provide stated Data Protection Impact
Assessments.
e)
That in respect of Leeds Public E-Bike Share, the
Combined Authority approves that:
i)
the Leeds Public E-Bike Share Scheme proceeds
through decision point 2 (strategic outline case) and work
commences on Activity 4 (full business case).
ii)
an indicative approval to the Combined
Authority’s contribution of £2,000,000. The total
scheme value is £2,394,178.
iii)
future approvals are made in accordance with the
assurance pathway and approval route outlined in the submitted
report and where required, any change requests are delegated to the
Transport Committee. This will be subject to the scheme remaining
within the tolerances outlined in the submitted report.
f)
That in respect of the Business Productivity
Programme, the Combined Authority approves that:
i)
the Business Productivity Programme proceeds through
decision point 2 (strategic outline case) and decision point 4
(full business case) and work commences on activity 5
(delivery).
ii)
approval to the Combined Authority’s
contribution of £4,500,000 is given.
iii)
future approvals are made in accordance with the
assurance pathway and approval route outlined in the submitted
report and where required any change requests are delegated to the
Business, Economy, and Innovation Committee. This will be subject
to the scheme remaining within the tolerances outlined in the
submitted report.
g)
That in respect of Skills Bootcamps, the Combined
Authority approves that, subject to confirmation that DfE funding
has been secured and the amount awarded::
i)
the Skills Bootcamps scheme
proceeds through decision point 2 (strategic outline case) and
decision point 4 (full business case) and work commences on
activity 5 (delivery).
ii)
approval is given to accept and spend up to
£3,689,000 from the Department for Education bid, subject to
the successful outcome of the bid. The total scheme value is
£3,689,000.
iii)
future approvals are made in accordance with the
assurance pathway and approval route outlined in the submitted
report and where required, any change requests are delegated to the
Employment and Skills Committee. This will be subject to the scheme
remaining within the tolerances outlined in the submitted
report.
h)
That in respect of York Central, in order for schemes to be delivered within tight
timescales, the Combined Authority approves:
i)
the delegation of authority to the Place,
Regeneration and Housing Committee, to approve the York Central
scheme in accordance with the Assurance Framework (Full Business
Case with finalised costs), so that delivery can commence in line
with delivery timeframes.
i) That in respect of the Contribution to Capital Programme Update – March 2022, the Combined Authority notes the release of the further Call for Projects for the Brownfield Housing Fund.
Minutes:
City Region Sustainable Transport Settlement (CRSTS) Capacity Funding
This will support the development of the pipeline of future schemes and the development of the CRSTS programme itself, increasing capacity and skills within the Combined Authority and partner councils. .
Gainshare Capacity Funding
Officers explained the proposal to draw down £11.4m of funding to increase the capacity for the Combined Authority and partner authorities to develop pipelines for our investment priorities over the next three years. The support will benefit frontline specialist teams or individuals, with the option to source external consultancy if needed.
CRSTS Programme
Officers informed the members
that the Combined Authority is currently waiting on receiving
£830m of funding from a Department for Transport announcement
in Autumn 2021. The funding will support transport improvements,
walking and cycling improvements, public transport, accessibility,
safety initiatives, and ensuring that national and regional
priorities are met. Each project is a sub-programme within the
wider CRSTS programme, and it is proposed to release the first
tranche of the funding subject to funding confirmation in March,
with delivery to begin in April.
There are multiple funding pots comprising the CRSTS including the
Transforming Cities Fund, Mass Transit, Highways Maintenance,
Network Management, and Safer Roads, which were previously
separate. Because the Highways Maintenance budget is delivered on a
rolling programme, it is proposed to approve the first six months
of spend to allow projects to keep moving, amounting to £63.5
million, subject to confirmation of funding.
Members questioned
the difference between the total value of the programme and the
value of the DfT funding and suggested that any decision should be
subject to receiving confirmation of the funding to ensure there
are no gaps in delivery. Officers confirmed that the total value is
£1.2 billion with match funding, which will come from a
variety of sources and will be carefully monitored to ensure
delivery.
Members asked for confirmation that all authorities in the region
will benefit from new highways funding. Officers confirmed that
there has been an uplift in funding for highways maintenance..
Members pointed out that £430m of the funding has already been announced as part of other schemes. Officers confirmed that some schemes were already a part of the Transforming Cities programme, though approximately 33 of the 61 schemes are new, as well as a new sustainable transport programme. A list of all projects is currently being drafted alongside partners.
Transformational - West
Yorkshire Mass Transit
Officers noted this is the second largest element of CRSTS, with
some £200m allocated in principle for mass transit in West
Yorkshire. There is some existing development funding through the
transformational funding and transport fund that has supported the
mass transit work so far. The proposal is to move to the business
outline case, which will require more work with external partners
to consider options. Out of a potential £200m pot, £31m
is proposed for release subject to the final letter confirmation
from the DfT.
Members thanked the staff who have contributed so much time to the
project, especially considering the small size of the team in West
Yorkshire.
Leeds Public E-Bike Share
Officers explained this scheme was initially a part of the
Transforming Cities Fund, arising following a request from partners
to propose projects relating to clean growth. The project is now
presented as a strategic outline case and is seeking contribution
of £2 million towards a total of £2.4 million. The
scheme will deliver 630 E-bikes and 140 hubs,
and presents the opportunity to encourage wider E-bikes use.
There is a desire to introduce similar schemes across other areas
in West Yorkshire.
Questions were raised about the accessibility of the project,
officers responded that conversations are being had with sponsors
as the full business case is developed.
Business Productivity Programme
Officers explained that the scheme aims to boost small and medium sized businesses productivity by providing them with advisory support and grants. This will build upon the success of the Business Growth Programme, which was popular enough to have spent all of the previous funding. The proposal is to focus the programme on productivity for one year, to then bid for future funding in due course.
Members noted the success of previous schemes targeting improving productivity, and highlighted the benefits of creating jobs that are skilled and well-paid which in turn boosts outputs for business across the region. Members further noted the evidence that businesses which export are 25% more productive, and the potential links with the Trade Strategy.
Skills Bootcamps
Members were informed that the Combined Authority has been successful in securing £3.7 million of funding from the Department for Education to progress Skills Bootcamps. The project offers intensive flexible training courses that last 16 weeks, and will allow adults to access high quality training at level 3 and above. Courses will be offered in sectors where there are skills shortages such as digital and the green economy among others. The scheme targets the improvement of skills for 1000 individuals, and approval would allow the scheme to move into delivery.
York Central
Officers explained the scheme proposes up to £99.5 million of
housing and commercial developments on land adjacent to the York
Railway Station. The Combined Authority is contributing £23.5
million to the project through the West Yorkshire Transport Fund.
This had previously been approved but recommended to return to the
Combined Authority following changes. It is requested that the
final approval to this scheme is delegated to the Place,
Regeneration and Housing Committee due to the expediency required
for delivery.
Members raised the benefits of the project which will not be
limited to just the area around York station.
Contribution to Capital Programme Update March 2022
Officers noted that the Levelling Up White
Paper announced a further award of £22.2 million to West
Yorkshire Combined Authority for the Brownfield Housing
Fund. Members are asked to note a call
for projects is currently live, and were
encouraged to publicise the call to any partners who can put
forward an eligible bid.
Members raised frustrations that the funding has similar
restrictions to the previous Brownfield Housing Fund, but welcomed
the opportunity for innovative projects that reach out to their
communities.
Resolved:
a)
That in respect of CRSTS Capacity Funding,
the Combined Authority approves that:
i)
the CRSTS Capacity Fund scheme proceeds through decision point 2 to
4 (business justification) and work commences on activity 5
(delivery).
ii)
indicative approval is given to the Combined Authority’s
contribution of £7,400,000. The total scheme value is
£7,400,000.
iii)
approval to £2,756,411 for tranche 2 (of 3) is given,
allocated as detailed in Appendix 2 of the submitted report,
bringing the total approval to £5,756,411.
iv)
the Combined Authority enters into a Funding
Agreement with each of the councils for expenditure as detailed in
Appendix 2 of the submitted report.
v)
changes to allocations in iii) and iv) above
are delegated to the Senior Responsible Officer (Interim Director
of Policy and Development) of the CRSTS programme.
vi)
future approvals are made in accordance with
the assurance pathway and approval route outlined in the submitted
report and where required, any change requests are delegated to the
Transport Committee. This will be subject to the scheme remaining
within the tolerances outlined in the submitted report.
b)
That in respect of Gainshare Capacity
Funding, the Combined Authority approves that:
i)
the Gainshare Capacity Funding scheme
proceeds through decision point 2 to 4 (business justification) and
work commences on activity 5 (delivery).
ii)
approval to the total scheme value of
£11,400,000 is given, allocated as detailed in Appendix 4 of
the submitted report.
iii)
the Combined Authority enters into a Funding Agreement with each of
the councils for expenditure of up to £1,890,000.
iv)
future approvals are made in accordance with the assurance pathway
and approval route outlined in the submitted report and where
required, any change requests are delegated to the Finance,
Resources and Corporate Committee. This will be subject to the
scheme remaining within the tolerances outlined in the submitted
report.
c)
That in respect of the CRSTS Programme, the
Combined Authority approves that, subject to the successful outcome
of the bid to DfT:
i)
the City Region Sustainable Transport
Settlement (CRSTS) programme proceeds through decision point 2
(strategic outline case) and work commences on development of the
relevant business case for each individual scheme.
ii)
an indicative approval to the total programme value of
£830,000,000 is given. The total programme cost is
£1,231,994,853.
iii) approval of development and delivery costs of up to £63,455,916 for business case development and programme management costs is given as follows:
· Up to £30,311,916 for monitoring and evaluation, communications, consultation and engagement and Combined Authority programme management.
· Development costs of up to £3,000,000 to enable delivery partners to develop scheme business cases.
· Delivery and development costs of up to £30,144,000 for the development of strategic outline cases and quarter 1 and quarter 2 costs for the Highways Asset Management, Network Management and Safer Roads programme.
iv)
approval is given for the delegation of authority to the Combined
Authority’s Director of Delivery, following a recommendation
from the Programme Appraisal Team, to approve requests for business
case development costs, in accordance with the Assurance
Framework.
v)
approval is given for the delegation of authority to the Combined
Authority’s Managing Director, following a recommendation
from the Programme Appraisal Team, to approve the behaviour change
programme proceeding into delivery in accordance with the Assurance
Framework from the indicative allocation of
£10,550,000.
vi)
in order to ensure that schemes can be
delivered within the tight timescales, the Combined Authority
delegates authority to the Managing Director to amend the approval
and allocation of CRSTS if the DfT award differs from
£830,000,000, or if further changes to individual allocations
is required, as a result of changes to the programme and approaches
to delivery.
vii) The Combined Authority enters into Funding Agreements with partners councils for expenditure, for the Highways Asset Management, Network Management and Safer Roads programme, up to the amounts shown below:
· Bradford £6,486,308
· Calderdale £3,846,476
· Kirklees £6,161,288
· Leeds £9,281,288
· Wakefield £4,368,640
viii) Future approvals are made in accordance with the
assurance pathway and approval route outlined in the submitted
report and any change requests are delegated to the Transport
Committee, which will be subject to the scheme remaining within the
tolerances outlined in the submitted report.
d)
That in respect of Transformational - West Yorkshire Mass Transit,
the Combined Authority, subject to the conditions set by Programme
Appraisal Team:
i)
approves the West Yorkshire Mass Transit Programme proceeds through
Decision Point 2 and work commences on Activity 3 (outline business
case) for the Programme Integration Business Case and on Activity 2
(strategic outline case) for the four phased corridor projects
within the programme.
ii)
endorses the proposed Mass Transit Programme scope, ambition and
network and the approach to phase development of projects within
the overall programme.
iii)
notes that future assurance of any Mass Transit business case will
be “called in” by central government.
iv)
indicatively approves £200,000,000 (subject to grant
determination letter from government) to develop the West Yorkshire
Mass Transit programme. Total scheme value is to be
determined.
v)
approves development costs of £31,887,500 in order to progress each of the four phased project
business cases to Decision Point 2 (strategic outline case), and
the Programme Integration Business Case to Decision Point 3
(subject to Grant Determination letter from Government). This would
take the total project approval to £33,928,500.
vi)
approves that future approvals are made
in accordance with the Approval Pathways and Approval Routes
outlined in the submitted report and where required any change
requests are delegated to the Transport Committee. This will be
subject to the scheme remaining within the tolerances outlined in
the submitted report.
Conditions for approval of Activity 2 (SOC) for the Programme
Integration Business Case:
vii)
Provide full details of the optioneering and options appraisal
methodology, including clearly defined critical success factor
development and use, criteria on technology and route options,
low-cost options considered and first phase option criteria and
include how approval was managed at each stage.
viii)Provide information on cost
benchmarking exercise.
ix)
Provide stated Data Protection Impact Assessments.
e)
That in respect of Leeds Public E-Bike Share, the Combined
Authority approves that:
i)
the Leeds Public E-Bike Share Scheme proceeds through decision
point 2 (strategic outline case) and work commences on Activity 4
(full business case).
ii)
an indicative approval to the Combined Authority’s
contribution of £2,000,000. The total scheme value is
£2,394,178.
iii)
future approvals are made in accordance with the assurance pathway
and approval route outlined in the submitted report and where
required, any change requests are delegated to the Transport
Committee. This will be subject to the scheme remaining within the
tolerances outlined in the submitted report.
f)
That in respect of the Business Productivity Programme, the
Combined Authority approves that:
i)
the Business Productivity Programme proceeds through decision point
2 (strategic outline case) and decision point 4 (full business
case) and work commences on activity 5 (delivery).
ii)
approval to the Combined Authority’s contribution of
£4,500,000 is given.
iii)
future approvals are made in accordance with the assurance pathway
and approval route outlined in the submitted report and where
required any change requests are delegated to the Business,
Economy, and Innovation Committee. This will be subject to the
scheme remaining within the tolerances outlined in the submitted
report.
g)
That in respect of Skills Bootcamps, the Combined Authority
approves that, subject to confirmation that DfE funding has been
secured and the amount awarded:
i)
the Skills Bootcamps scheme proceeds through
decision point 2 (strategic outline case) and decision point 4
(full business case) and work commences on activity 5
(delivery).
ii)
approval is given to accept and spend up to £3,689,000 from
the Department for Education bid, subject to the successful outcome
of the bid. The total scheme value is £3,689,000.
iii)
future approvals are made in accordance with the assurance pathway
and approval route outlined in the submitted report and where
required, any change requests are delegated to the Employment and
Skills Committee. This will be subject to the scheme remaining
within the tolerances outlined in the submitted report.
h)
That in respect of York Central, in order
for schemes to be delivered within tight timescales, the
Combined Authority approves:
i)
the delegation of authority to the Place, Regeneration and Housing
Committee, to approve the York Central scheme in accordance with
the Assurance Framework (Full Business Case with finalised costs),
so that delivery can commence in line with delivery
timeframes.
i) That in respect of the Contribution to Capital Programme Update – March 2022, the Combined Authority notes the release of the further Call for Projects for the Brownfield Housing Fund.