West Yorkshire Combined Authority Head Office Accommodation Project

Decision:

Resolved: That in respect of West Yorkshire Combined Authority Head Office Accommodation Project Investment Committee approves that:

 

(a)  The West Yorkshire Combined Authority Head Office Accommodation

       project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

 

(b)  An indicative approval to the total project cost of £6.847 million is given.

      This will be funded entirely by the Combined Authority (from the approved

      budget for Corporate Projects), with full approval to spend being granted    

      once the scheme has progressed through the assurance process to  

      decision point 5 (full business case with finalised costs).

 

(c)   Future approvals are made in accordance with the assurance pathway

       and approval route set out in the submitted report following a

       recommendation by the Combined Authority’s Programme Appraisal

       Team. This will be subject to the scheme remaining within the tolerances

       outlined in the report.