Meeting: 25/04/2019 - West Yorkshire Combined Authority (Item 102)

Leeds Flood Alleviation Scheme 2

Additional documents:

Decision:

Resolved - That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Leeds Flood Alleviation Scheme Phase 2 proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs)

(ii)        That an indicative approval to the Combined Authority’s contribution of up to £3.9 million, which will be funded through Growth Deal 3 is given with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total project value is £112 million.

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5, through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

Minutes:

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Leeds Flood Alleviation Scheme Phase 2 proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs)

(ii)        That an indicative approval to the Combined Authority’s contribution of up to £3.9 million, which will be funded through Growth Deal 3 is given with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total project value is £112 million.

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5, through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.