Capital Spending and Project Approvals

Meeting: 13/03/2019 - ARCHIVED - West Yorkshire and York Investment Committee (Item 60)

60 Capital Spending and Project Approvals pdf icon PDF 414 KB

Additional documents:

Decision:

Resolved:

 

(i)        In respect of Leeds City Region Growth Service, the Investment Committee recommends to the Combined Authority:

(a)        That the Leeds City Region Growth Service project proceeds through decision point 2 (case paper) and work commences on activity 5 (full business case).

(b)        That an indicative approval to the total project costs of £3,401,756, of which the Combined Authority contribution will be £2,465,413 (which will be funded through £764,535 from the BEIS Growth Hub funding and £1,700,878 from the ESIF funding is given with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The remaining £936,343 will be funded by Leeds City Region District Partners.

(c)        That the Combined Authority delegates the authority to enter into a funding agreement with Ministry for Housing, Communities and Local Government (ESIF) and BEIS (Growth hub funding) to the Combined Authority’s Managing Director.

(d)        That the Combined Authority delegates the authority to enter into or amend funding agreements with the local authorities to the Combined Authority’s Managing Director.

(e)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(ii)       In respect of Resource Efficiency Fund 2, the Investment Committee recommends to the Combined Authority:

(a)        That the Resource Efficiency Fund 2 project proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs). 

(b)        That indicative approval to the total project value for both regions (Leeds City Region and four North Yorkshire districts) of £6.293m is given as detailed below, with full approval to spend being granted once the project has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(c)        That Leeds City Region element of the project of £4.644 million (subject to a successful ERDF application), of which £2.751 million will be funded by the Combined Authority (£2 million ERDF funding for Leeds City Region and £751,137 from the Leeds City Region Local Growth Fund). The remaining funding will be from £1.893 million SME match.

(d)        That York, North Yorkshire and East Riding element of the project of £1.649 million (subject to a successful ERDF application) of which £1.035 million will be funded by the Combined Authority (from £824,522 ERDF funding and £210,122 from the York, North Yorkshire and East Riding region Local Growth Fund, which North Yorkshire County Council as the accountable body for the York, North Yorkshire and East Riding LEP will transfer to the Combined Authority and the Combined Authority will be the accountable body for its expenditure for the purposes of this scheme). The remaining scheme costs of £614,000 will be from SME match funding.

(e)        That the  ...  view the full decision text for item 60

Minutes:

The Committee considered a report on proposals for the progression of, and funding for, a number of West Yorkshire Combined Authority supported projects, including West Yorkshire plus Transport Fund (Transport Fund) and Growth Fund at stages 1, 2 and 3 of the Combined Authority’s assurance process.

 

Members discussed the proposals for the progression of the following seven schemes which were detailed in the submitted report:

 

·         Leeds City Region Growth Service

·         Resource Efficiency Fund 2

·         Leeds Flood Alleviation Scheme 2

·         A61 (North) Bus Priority Corridor

·         Wakefield South East Gateway

·         Dewsbury Riverside

·         York Central: Access Road and Station Access Improvements

 

Members were given a presentation on the proposals for the York Central: Access Road and Station Access Improvements scheme.  Approval was sought for the West Yorkshire plus Transport Fund to contribute to the funding of a new access road into York Central, a series of improvements to the front of York station and pedestrian access improvements into the York Central site.  It was noted that delivery of these elements were dependent on City of York Council funding and on securing match funding from the Housing Infrastructure Fund.

 

Copies of the business case summaries for the schemes were attached at Appendices 2-8 of the submitted report. 

 

The Committee also considered a change request in respect of the following scheme, details of which were provided in the submitted report:

 

·         Superfast West Yorkshire and York – Contract 3

 

It was reported that the following decision points and change requests had been approved since the last meeting through the agreed delegation to the Combined Authority’s Managing Director:

 

·         Harrogate Road/New Line Junction Improvement

·         Apprenticeship Grants for Employers (AGE)

·         Natural Flood Management – Upper Aire

 

Details of the change requests and delegated approval for the schemes were outlined in the report.

 

Resolved:

 

(i)        In respect of Leeds City Region Growth Service, the Investment Committee recommends to the Combined Authority:

(a)        That the Leeds City Region Growth Service project proceeds through decision point 2 (case paper) and work commences on activity 5 (full business case).

(b)        That an indicative approval to the total project costs of £3,401,756, of which the Combined Authority contribution will be £2,465,413 (which will be funded through £764,535 from the BEIS Growth Hub funding and £1,700,878 from the ESIF funding is given with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The remaining £936,343 will be funded by Leeds City Region District Partners.

(c)        That the Combined Authority delegates the authority to enter into a funding agreement with Ministry for Housing, Communities and Local Government (ESIF) and BEIS (Growth hub funding) to the Combined Authority’s Managing Director.

(d)        That the Combined Authority delegates the authority to enter into or amend funding agreements with the local authorities to the Combined Authority’s Managing Director.

(e)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point  ...  view the full minutes text for item 60