A650 Bradford to Keighley Corridor (Hard Ings)

Meeting: 13/12/2018 - West Yorkshire Combined Authority (Item 62)

A650 Bradford to Keighley Corridor (Hard Ings)

Additional documents:

Decision:

Resolved:

In respect of A650 Bradford to Keighley Corridor (Hard Ings) –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Hard Ings Road Improvements, Keighley project proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs)

(ii)        That an indicative approval to the total project value of £10.3 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs)

(iii)       That further development costs of £2.718 million are approved in order to progress the scheme to decision point 5 (full business case with finalised costs) to be funded from the West Yorkshire plus Transport Fund, taking the total project approval to £3.86 million.

(iv)       That the Combined Authority enters into an addendum to the existing funding agreement with Bradford City Council for expenditure of up to £3.86 million from the West Yorkshire plus Transport Fund

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.