Corridor Improvement Programme - Calderdale - A629 North – Orange Street

Meeting: 03/02/2022 - West Yorkshire Combined Authority (Item 83)

83 Capital Spending and Project Approvals pdf icon PDF 557 KB

(Lead Member: The Mayor, Director: Melanie Corcoran)

Additional documents:

Decision:

Resolved: The Combined Authority approves that:

 

a)    the CIP - A629(N) – Ogden to Orange Street Roundabout scheme proceeds through decision 3 (outline business case) and work commences on activity 4 (full business case).

b)    an indicative approval to the Combined Authority’s contribution of £6,100,000 is given. The total scheme value is £7,010,000.

c)    additional development costs of £1,180,000 are approved in order to progress the scheme to decision point 4 (full business case), taking the total scheme approval to £1,810,000.

d)    the Combined Authority enters into a funding agreement with Calderdale Metropolitan Borough Council for expenditure of up to £1,810,000.

e)    future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.

Minutes:

The Combined Authority considered a report on proposals for the progression of, and funding for, West Yorkshire Combined Authority supported projects that had been considered at stages 1, 2 and 3 of the Combined Authority’s assurance process.

The Connectivity Infrastructure Plan (CIP) A629 (North) Ogden to Orange Street Roundabout scheme was considered for approval, and had come directly to the Combined Authority due to expediency of delivery. The project was seeking indicative approval of a contribution of £6.1m from the Combined Authority, and was expected to improve access to education, training and employment opportunities, as well as reducing standing traffic. Approval was sought for development costs of £1.18 million, and for the scheme to proceed from decision point 3 and for work to commence on the full business case.

 

Resolved: The Combined Authority approves that:

 

a)    The CIP - A629(N) – Ogden to Orange Street Roundabout scheme proceeds through decision 3 (outline business case) and work commences on activity 4 (full business case).

b)    An indicative approval to the Combined Authority’s contribution of £6,100,000 is given. The total scheme value is £7,010,000.

c)     Additional development costs of £1,180,000 are approved in order to progress the scheme to decision point 4 (full business case), taking the total scheme approval to £1,810,000.

d)    The Combined Authority enters into a funding agreement with Calderdale Metropolitan Borough Council for expenditure of up to £1,810,000.

e)    Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.