Purpose:

Approval for the scheme to progress through Activity 2 (Strategic Outline Case).

Decision:

Resolved:  In respect of Network Navigation - West Yorkshire -

That following a recommendation from the Investment Committee, the  Combined Authority approves:

(i)     That the Network Navigation project proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case).

(ii)    That an indicative approval to the total package value of £15.20 million is given from the Transforming Cities Fund and £300,000 from Integrated Transport Bloc funding with full approval to spend once the package has progressed through the assurance process to decision point 5.

(iii)   That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the package remaining within the tolerances outlined in the report.

Report author: Fiona Limb

Publication date: 07/09/2020

Date of decision: 04/09/2020

Decided at meeting: 04/09/2020 - West Yorkshire Combined Authority

Effective from: 15/09/2020