This scheme will deliver a dedicated, flexible business support service for the Leeds City Region’s larger small and medium enterprises (SMEs).
PMO Reference: -
Stage: 1 (Eligibility)
Decision Point: 2 (Case Paper)

Decision:

Resolved - That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Leeds City Region Growth Service project proceeds through decision point 2 (case paper) and work commences on activity 5 (full business case).

(ii)        That an indicative approval to the total project costs of £3,401,756, of which the Combined Authority contribution will be £2,465,413 (which will be funded through £764,535 from the BEIS Growth Hub funding and £1,700,878 from the ESIF funding is given with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).  The remaining £936,343 will be funded by Leeds City Region District Partners.

(iii)       That the Combined Authority delegates the authority to enter into a funding agreement with Ministry for Housing, Communities and Local Government (ESIF) and BEIS (Growth hub funding) to the Combined Authority’s Managing Director.

(iv)       That the Combined Authority delegates the authority to enter into or amend funding agreements with the local authorities to the Combined Authority’s Managing Director.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team.  This will be subject to the scheme remaining within the tolerances outlined in the report.