Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable work to commence on the Upper Aire
phase of the Natural Flood Management programme, leading to the
delivery of hundreds of small individual natural flood management
interventions spread across a large area of the Upper Aire
catchment, working with multiple land owners, to slow the flow of
water before it reaches the main river. This helps support other,
more conventional, flood schemes to make a more cost effective
overall solution – bringing with it wider environmental
benefits.
To approve that the Growing Resilience Natural
Flood Management Phase 2: Upper Aire project proceeds through
decision point 5 and work commences on activity 6, delivery.
To give approval to the total project value of £408,047,
which includes a £388,000 contribution from the Local Growth
Fund.
To approve that the Combined Authority enter into a Funding
Agreement with Yorkshire Wildlife Trust for expenditure of up to
£388,000 from the Local Growth Fund.
None
Publication date: 28/02/2019
Date of decision: 15/02/2019