Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
The purpose of the scheme is to increase car parking capacity at Mytholmroyd Railway Station. Stage 2 (Development), Decision 5 (Full Business Case with Finalised Costs).
To approve that:
· The Rail Park & Ride – Mytholmroyd project proceeds through Decision Point 5 and work commences on Activity 6 (Delivery).
· That full approval to the total project value of £3.64 million is given from the West Yorkshire plus Transport Fund, of which £171,828 is development costs spent from previous funding approvals
· The Combined Authority enter into a Section 56 Agreement with Arriva Rail North (Northern) for £3,361,319 to deliver the scheme.
· The Combined Authority enter into a community grant agreement with the Mytholmroyd Station Partnership for up to £3,000 for delivery of a package of environmental works at the station.
To enable delivery of a new car park at Mytholmroyd railway station which would have 203 parking spaces including 10 Blue Badge bays. This would deliver much needed parking capacity on the Calder Valley line.
Publication date: 18/10/2018
Date of decision: 16/11/2018
Effective from: 23/11/2018