Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to progress through
Activity 2 (Strategic Outline Case) and work commence on Activity 4
(Full Business Case).
Resolved:
That the Combined Authority approves that:
a)
the Leeds Public E-Bike Share Scheme proceeds
through decision point 2 (strategic outline case) and work
commences on Activity 4 (full business case).
b)
an indicative approval to the Combined
Authority’s contribution of £2,000,000. The total
scheme value is £2,394,178.
c)
future approvals are made in accordance with the
assurance pathway and approval route outlined in the submitted
report and where required, any change requests are delegated to the
Transport Committee. This will be subject to the scheme remaining
within the tolerances outlined in the submitted report.
Report author: Freedom.Info@westyorks-ca.gov.uk
Publication date: 18/03/2022
Date of decision: 17/03/2022
Decided at meeting: 17/03/2022 - West Yorkshire Combined Authority
Effective from: 26/03/2022