Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to progress through
Activity 3 (Outline Business Case)
(i) The TCF Heckmondwike Bus Hub scheme proceeds through decision
point 3 (outline business case) and work commences on activity 4 (full
business case).
(ii) An indicative approval to the Combined Authority’s contribution of
£4,970,541. The total scheme value is £4,970,541.
(iii) Development costs of £328,000 are approved in order to progress the
scheme to decision point 4 (full business case) taking the total scheme
approval to £643,000.
(iv) The Combined Authority enters into an addendum to the existing funding agreement with Kirklees Council for expenditure of up to £643,000.
(v) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report
Publication date: 03/03/2022
Date of decision: 03/03/2022
Effective from: 04/03/2022