Transforming Cites Fund - Heckmondwike Bus Hub

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the scheme to progress through Activity 3 (Outline Business Case)

Decision:

 

(i) The TCF Heckmondwike Bus Hub scheme proceeds through decision

point 3 (outline business case) and work commences on activity 4 (full

business case).

 

(ii) An indicative approval to the Combined Authority’s contribution of

£4,970,541. The total scheme value is £4,970,541.

 

(iii) Development costs of £328,000 are approved in order to progress the

scheme to decision point 4 (full business case) taking the total scheme

approval to £643,000.

 

(iv) The Combined Authority enters into an addendum to the existing funding agreement with Kirklees Council for expenditure of up to £643,000.

 

(v) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report

Publication date: 03/03/2022

Date of decision: 03/03/2022

Effective from: 04/03/2022