Decision Maker: Director, Finance & Commercial Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable funding to be in place for
preparatory work to continue on the White Rose Station scheme in
advance of the signing of a new Grant Agreement with the developer.
The station will be a new rail station with associated access
situated on the existing Leeds – Huddersfield Line alongside
the White Rose Office Park, Millshaw, Leeds, between Morley and
Cottingley on the Transpennine route.
To approve that
• The change request to re-profile the existing LPTIP
allocation on the scheme to use the unspent £741,000 from the
LPTIP Grant Agreement 1 approval to fund immediate works, required
to maintain the contractors programme and hit key pre booked
possession dates, is approved.
• The Combined Authority enters into a deed of variation to
the existing Grant Agreement with the developer.
Publication date: 02/09/2021
Date of decision: 27/08/2021