Decision details

Corridor Improvement Programme: Calderdale - A58 - A672 Corridor

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the scheme to progress through Activity 5 (Full Business Case plus finalised costs)

Decision:

To approve that

 

·        The Corridor Improvement Programme A58/A672 scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·        Approval to the total scheme cost of £4.947 million, to be funded through the West Yorkshire plus Transport Fund, is given. 

 

·        The Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for total expenditure up to £4.947 million from the West Yorkshire plus Transport Fund.

 

Reasons for the decision:

To enable delivery to commence on this scheme which consists of a package of work to improve highway traffic flow for the benefit of all road users, particularly improved bus, walking and cycling facilities, along the A58/A672 in Calderdale, between Halifax and the M62 Junction 22 via Sowerby Bridge, Ripponden, and Rishworth.

Publication date: 02/08/2021

Date of decision: 30/07/2021

Effective from: 10/08/2021

Accompanying Documents: