Rail Parking Package – Shipley

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To enable development work to continue on the scheme which would deliver an increase in car parking spaces at Shipley Rail Station from the current 140 spaces to a total of 227 spaces.

Decision:

To approve that the change request to the Rail Parking Package – Shipley scheme to increase the previously approved Section 56 by £86,939 (taken from the indicative approval of £2.55 million) to progress design feasibility at Shipley Railway Station is approved. This will take the overall approval for Section 56 to £252,371.

To approve that the Combined Authority enters into an addendum to the S56 Agreement with Northern Rail for an additional £86,939.

Publication date: 03/03/2021

Date of decision: 26/02/2021