Decision details

Capital Spending and Project Approvals (to be considered at Investment Committee on 5 December 2018)

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

Resolved:

 

(a)       In respect of the Investment Readiness Project –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Investment Readiness project proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs).

(ii)        That an indicative approval to the Combined Authority’s contribution of £1.429 million is given (which will be funded from £714,500 from the Leeds City Region Business Rates Pool and £714,500 from ESIF), with Full Approval to spend being granted once the scheme has progressed through the Assurance Process to Decision Point 5. The total project value is £1.429 million with funding already secured.

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team subject to the scheme remaining within the assurance tolerances outlined within the report.

(b)       In respect of the Transformational – A6120 Leeds Northern Outer Ring Road Improvements, Leeds –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the A6120 Leeds Northern Outer Ring Road Improvements (A647 to A65) proceeds through decision point 2 and work commences on the feasibility study.

(ii)        That an expenditure approval is given to the total value of £392,500 to Leeds City Council to fund a feasibility study.

(iii)       That the Combined Authority enter into a funding agreement with Leeds City Council for expenditure of up to £392,500 to be funded from the West Yorkshire plus Transport Fund.

(iv)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(c)       In respect of Corridor Improvement Programme Phase 1 – A647 Dawsons Corner –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Dawson’s Corner project proceeds through decision point 3 and work commences on activity 4 (full business case).

(ii)        That an indicative approval is given to the total project value of £20.159 million, with the Combined Authority’s contribution of £19 million (which will be funded through £15 million from the CIP Phase 1 fund and £4 million from the LPTIP fund) is given with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total project value is £20.159 million.

(iii)       That  development costs of £1.599 million, (including £499,000 additional development costs and £1.1 million land assembly costs) are approved in order to progress the scheme to decision point 5 (full business case with finalised costs), taking the approval to £2.607 million

(iv)       That the Combined Authority issue an addendum to the existing funding agreement with Leeds Council for additional expenditure of up to £1.599 million from the West Yorkshire plus Transport Fund taking the total value to £2.607 million.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(d)       In respect of Corridor Improvement Programme Phase 1 – Dyneley Arms –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Dyneley Arms junction project proceeds through decision point 3 and work commences on activity 4 (full business case) and 5.

(ii)        That an indicative approval to the total project value of £2.747 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs)

(iii)       That additional development costs of £373,000 (which include £250,000 for land assembly) are approved in order to progress the scheme to decision point 5 (full business case with finalised costs) taking the total approval to £775,000.

(iv)       That the Combined Authority issues an addendum to the existing funding agreement with Leeds Council for additional expenditure of up to £373,000 from the West Yorkshire plus Transport Fund (giving a total funding agreement value of £775,000).

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(e)       In respect of Corridor Improvement Programme Phase 1 – Fink Hill scheme –

That following a recommendation from the Investment Committee, the   Combined Authority approves:

(i)         That the Corridor Improvement Programme Phase 1 Fink Hill project proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case).

(ii)        That an indicative approval to the total project value of £4.150 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That additional development costs of £404,000 are approved in order to progress the scheme to decision point 4 (full business case) taking the total project approval to £519,000.

(iv)       That the Combined Authority enter into an addendum to the existing funding agreement with Leeds City Council for additional expenditure of up to £404,000 from the West Yorkshire plus Transport Fund taking the total value to £519,000.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject remaining within the tolerances outlined in the report.

(f)        In respect of Corridor Improvement Programme Phase 1 – A650 Newton Bar scheme –

That the Combined Authority approves

(i)         That the Corridor Improvement Programme Phase 1 A650 Newton Bar project proceeds through decision point 3 and work commences on activity 4 (full business case).

(ii)        That an indicative approval to the total project value of £6.752 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That development costs of £129,800 are approved in order to progress the scheme to decision point 4 (full business case) taking the total project approval to £204,800.

(iv)       That the Combined Authority enters into an addendum to the existing funding agreement with Wakefield Council for additional expenditure of up to £129,800 from the West Yorkshire plus Transport Fund taking the total value to £204,800.

(v)        That future approvals are made in accordance with the §assurance pathway and approval route outlined in the submitted report (including through delegation to the Combined Authority’s Managing Director at decision points 4 and 5) following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(g)       In respect of Institute of High Speed Railways and System Integration (IHSRSI) –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Institute for High Speed Rail and System Integration scheme Phase 1 proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs).

(ii)        That an indicative approval to the Combined Authority’s contribution of £13.047 million is given, which will be funded through over-programming against the Local Growth Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total Phase 1 value is £26.093 million (The University of Leeds will contribute match funding of £13.047 million).  The Combined Authority’s contribution is capped at £13.047 million regardless of any future increases to the total scheme costs.

(iii)       That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 5 (full business case with finalised costs) through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report

(h)       In respect of the Business Growth Programme –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the change request to the Business Growth Programme is approved to provide additional £7 million of funding to the Business Growth Programme. This will be funded from over programming against the Local Growth Fund.  This would take the expenditure approval for the total programme to £34 million.

(ii)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report.  This will be subject to the scheme remaining within the tolerances outlined within the report.

Publication date: 14/12/2018

Date of decision: 13/12/2018

Decided at meeting: 13/12/2018 - West Yorkshire Combined Authority

Effective from: 22/12/2018

Accompanying Documents: