Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
The scheme focuses on traffic improvements at
two junctions: the A6177 Whetley Lane / Toller Lane junction and
the A6177 Thornton Road / Cemetery Road junction.
PMO Reference: WYTF-PA4-038A-10
Stage: 2 (Development)
Decision Point: 3 (Outline Business Case)
Resolved - That following a recommendation from the Investment Committee, the Combined Authority approves:
(i) That the A6177 Thornton Road / Toller Lane scheme proceeds through decision point 3 and work commences on activity 4 (full business case).
(ii) That an indicative approval to the total project value of £9.662 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(iii) That additional development costs of £721,670 are approved in order to progress the scheme to decision point 5 (full business case with finalised costs) taking the total project approval to £946,670.
(iv) That the Combined Authority enters into an addendum to the existing funding agreement with Bradford Council for additional expenditure of up to £721,670 from the West Yorkshire plus Transport Fund, taking total value of the funding agreements to £946,670.
(v) That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision points 4 and 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.
Report author: Andrew Norman
Publication date: 25/04/2019
Date of decision: 25/04/2019
Decided at meeting: 25/04/2019 - West Yorkshire Combined Authority
Effective from: 03/05/2019