Programme to develop Inclusive Growth Corridor
Plans and carry-out initial feasibility works on identified
schemes.
Resolved - In respect of Inclusive Growth Corridors and the Transformational Fund (decision point 2 case paper) –
That following a recommendation from the Investment Committee, the Combined Authority approves:
(a) That the Inclusive Growth Corridors and the Transformational Fund Phase 1 proceeds through decision point 2 (case paper) and work commences on the completion of the Corridor Plans and Connectivity Strategy.
(b) That indicative approval to the total programme value of £7million is given and full approval of £2.395million for Phase 1 is approved.
(c) That any change requests relating to Phase 1 are made in accordance with the approval pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.
Report author: Tom Gifford
Publication date: 05/04/2018
Date of decision: 05/04/2018
Decided at meeting: 05/04/2018 - West Yorkshire Combined Authority
Effective from: 18/04/2018