Issue details

Corridor Improvement Programme: Wakefield - A650 Newton Bar

To approve that

 

·        The Corridor Improvement Programme Wakefield A650 Newton Bar scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·        Approval to an additional £8.285 million from the West Yorkshire plus Transport Fund (WY+TF) is given, taking the total approval from the WY+TF to £8.635 million. The total scheme value is £8.720 million.

 

·        The Combined Authority enters into a funding variation agreement with Wakefield Council for expenditure of up to £8.635 million from the WY+TF.

 

Decision type: Key

Reason Key: Expenditure/Savings > £1 million;

Decision status: Recommendations Approved

Notice of proposed decision first published: 12/03/2021

Decision due: 23 Apr 2021 by Chief Executive

Contact: James Bennett Email: james.bennett@westyorks-ca.gov.uk.