To approve that
•The change request to the LPTIP Real Time Phase 2 to increase
costs by £0.300 million is approved.
•Approval to the LPTIP Real Time Phase 2 scheme value of
£0.300 million is given from the Leeds Public Transport
Investment Programme, taking the total approval from the LPTIP to
£5.860 million.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 31/03/2021
Decision due: 20 Nov 2020 by Chief Executive
Contact: Ben Still Email: ben.still@westyorks-ca.gov.uk.