Issue details

Real Time Information - Phase 2 - Change Request

To approve that
•The change request to the LPTIP Real Time Phase 2 to increase costs by £0.300 million is approved.
•Approval to the LPTIP Real Time Phase 2 scheme value of £0.300 million is given from the Leeds Public Transport Investment Programme, taking the total approval from the LPTIP to £5.860 million.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 31/03/2021

Decision due: 20 Nov 2020 by Chief Executive

Contact: Ben Still Email: ben.still@westyorks-ca.gov.uk.

Decisions