To approve a change request for Phase 1 of the
Corridor Improvement Programme and in addition seek Decision Point
3 approval (outline business case) to approve the progression of a
number of schemes which form part of the Phase 1 of the Corridor
Improvement Programme. The schemes which may be progressed to this
meeting are:
Leeds - Dynley Arms Junction
Leeds - Fink Hill
Leeds - Dawsons Corner
Bradford - Great Horton/ Cross lane
Wakefield - Newton Bar
PMO Reference: WYTF-PA4-038A
Stage: 2 (Delivery)
Decision Point: Various
Decision type: Key
Reason Key: Expenditure/Savings > £1 million;
Decision status: Recommendations Approved
Notice of proposed decision first published: 14/11/2018
Decision due: 13 Dec 2018 by West Yorkshire Combined Authority
Lead director: Chief Operating Officer
Contact: Andrew Norman Email: andrew.norman@westyorks-ca.gov.uk.