Issue details

Corridor Improvement Programme (Phase 1)

To approve a change request for Phase 1 of the Corridor Improvement Programme and in addition seek Decision Point 3 approval (outline business case) to approve the progression of a number of schemes which form part of the Phase 1 of the Corridor Improvement Programme. The schemes which may be progressed to this meeting are:

Leeds - Dynley Arms Junction
Leeds - Fink Hill
Leeds - Dawsons Corner
Bradford - Great Horton/ Cross lane
Wakefield - Newton Bar

PMO Reference: WYTF-PA4-038A
Stage: 2 (Delivery)
Decision Point: Various

Decision type: Key

Reason Key: Expenditure/Savings > £1 million;

Decision status: Recommendations Approved

Notice of proposed decision first published: 14/11/2018

Decision due: 13 Dec 2018 by West Yorkshire Combined Authority

Lead director: Chief Operating Officer

Contact: Andrew Norman Email: andrew.norman@westyorks-ca.gov.uk.

Decisions

Agenda items