Issue details

A629 Phase 1b

To approve the Change Request for the A629 phase 1b to allow for additional funding to develop the full business case and full business case with finalised costs on the revised programme as identified. To increase the development costs by £4.545 million in order to continue progressing the scheme to full business case, and to approve an addendum to the existing funding agreement between the Combined Authority and Calderdale MBC for this additional expenditure.

Decision type: Key

Reason Key: Expenditure/Savings > £1 million;

Decision status: Recommendations Approved

Notice of proposed decision first published: 06/06/2018

Decision due: 27 Mar 2018 by Chief Executive

Contact: Jess McNeill Email: jessica.mcneill@leeds.gov.uk.