To approve the Change Request for the A629
phase 1b to allow for additional funding to develop the full
business case and full business case with finalised costs on the
revised programme as identified. To increase the development costs
by £4.545 million in order to continue progressing the scheme
to full business case, and to approve an addendum to the existing
funding agreement between the Combined Authority and Calderdale MBC
for this additional expenditure.
Decision type: Key
Reason Key: Expenditure/Savings > £1 million;
Decision status: Recommendations Approved
Notice of proposed decision first published: 06/06/2018
Decision due: 27 Mar 2018 by Chief Executive
Contact: Jess McNeill Email: jessica.mcneill@leeds.gov.uk.