Transforming Cities Fund - Tadcaster Road Corridor Improvements

That subject to the conditions set by the Programme Appraisal Team, the Chief Executive approves that:

(i)             The TCF Tadcaster Road scheme proceeds through decision point 2 to 4 (business justification) and work commences on activity 5 (delivery).

(ii)            Approval to the Combined Authority’s contribution of £1,356,000, taking the total scheme approval to £1,420,000. The total scheme value is £1,420,000.

(iii)          The Combined Authority enters into an addendum to the existing Funding Agreement with City of York Council for expenditure of up to £1,420,000.

(iv)          Future approvals are made in accordance with the assurance pathway and approval route outlined in the report attached to this decision. This will be subject to the scheme remaining within the tolerances outlined in the attached report

 

Conditions

The following conditions have been set by PAT to gain Approval to Proceed to Delivery:

(i)             The final agreed tender cost of the scheme must be confirmed to come within the available funding, and a detailed cost breakdown and cost plan from the contractor provided as evidence.

(ii)            If a funding gap exists which cannot be bridged by either additional funding from CYC or value engineering, the scheme will be brought back to PAT for approval of any changes to the current design.

(iii)          The objectives are updated to ensure that they are all SMART, the specific outputs and benefits are confirmed, and a Monitoring and Evaluation Plan is provided.

(iv)          A construction programme (Gantt) is supplied for the works, covering both the core maintenance works and TCF works for Tadcaster Road.

 

Decision type: Key

Reason Key: Expenditure/Savings > £1 million;

Decision status: Recommendations Approved

Notice of proposed decision first published: 21/06/2022

Decision due: 13 Sep 2022 by Chief Executive
Reason: The reasons for the decision are as set out in a published report to the Combined Authority meeting of 9 September (Agenda Item 9), which was cancelled as a mark of respect following the sad announcement of the passing of Her Majesty the Queen

Contact: Email: Freedom.Info@westyorks-ca.gov.uk Email: governanceservices@westyorks-ca.gov.uk.

Decisions

Agenda items

Documents