Issue details

TCF - Programme (Change Request)

Approval to the change request for the TCF Programme giving approval to: 

·       Total additional development costs of £7,671,000.

·       The Combined Authority entering into variations to the existing Funding Agreements

 -    with Calderdale Council for:

o   £596,000 for Elland Rail Station Access

o   £2,150,000 for Halifax Rail Station Gateway

-       with Kirklees Council for:

o   £450,000 for Dewsbury – BatleyChidswell Corridor

o   £450,000 for Dewsbury – Cleckheaton Sustainable Travel Corridor

o   £550,000 for Dewsbury Town Centre Walking and Cycling Improvements

o   £750,000 for Huddersfield Rail Station Connections

o   £700,000 for A629 Wakefield Road Sustainable Travel Corridor

-       with Leeds City Council for:

o   £150,000 for A64 Bus – Cycle – Walking Improvements

o   £150,000 for Leeds E-bike Hire Scheme

-       with North Yorkshire County Council for:

o   £400,000 for Harrogate Railway Station Gateway

o   £450,000 for Skipton Railway Station Gateway

·       £875,000 development costs for the Combined Authority-led element of Dewsbury Bus Station.

 

Decision type: Key

Reason Key: Expenditure/Savings > £1 million;

Decision status: Recommendations Approved

Notice of proposed decision first published: 16/12/2021

Decision due: 28 Jan 2022 by Chief Executive

Contact: Email: Freedom.Info@westyorks-ca.gov.uk.

Decisions