Resolved: That in respect of the York Northern Outer Ring Road, the Combined Authority approves:
i)
The change request to the York Northern Outer Ring
Road project to bring together the roundabout junction upgrade
scheme and the dualling scheme and their associated funding
allocations, into one combined scheme, with total scheme costs of
£65,193,000, and for development costs of £3,438,000
from the West Yorkshire plus Transport Fund to progress the
combined scheme to full business case, bringing the total
development costs to £9,019,000 from the West Yorkshire plus
Transport Fund.
ii)
That the Combined Authority enters into an addendum
to the existing funding agreement with City of York Council for
expenditure of up to £9,019,000 from the West Yorkshire +
Transport Fund.
iii) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the submitted report.