Corridor Improvement Programme: Calderdale - A646 - A6033 Corridor

02/08/2021 - Corridor Improvement Programme: Calderdale - A646 - A6033 Corridor

To approve that

 

·        The Corridor Improvement Programme Calderdale A646-A6033 Corridor scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·        Approval to the total Combined Authority contribution of £3.988 million, to be funded through the West Yorkshire plus Transport Fund, is given. The total scheme value is £4.313 million, with a £0.325 million match contribution from Calderdale Council.

 

·        The Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for expenditure of up to £3.988 million from the West Yorkshire plus Transport Fund.