Corridor Improvement Programme: Calderdale - A58 - A672 Corridor

02/08/2021 - Corridor Improvement Programme: Calderdale - A58 - A672 Corridor

To approve that

 

·        The Corridor Improvement Programme A58/A672 scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·        Approval to the total scheme cost of £4.947 million, to be funded through the West Yorkshire plus Transport Fund, is given. 

 

·        The Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for total expenditure up to £4.947 million from the West Yorkshire plus Transport Fund.