Resolved: That in respect of the CityConnect Phase 3 Canals - Huddersfield Narrow Canal (HNC) Phase 2, the Combined Authority approves, subject to the conditions set by PAT stated in the submitted report:
(i) That the
CityConnect Phase 3 Canals –
Huddersfield Narrow Canal Phase 2 scheme proceeds through Decision
Point 4 (full business case) and work commences on Activity 5
(Delivery).
(ii) That approval
to the Combined Authority’s contribution of £1.371
million (which will be funded through £0.643 million from the
West Yorkshire plus Transport Fund and £0.728 million from
the Active Travel Fund) is given. The total scheme value is
£1.371 million.
(iii)
That the Combined Authority enters into an addendum to the existing
funding agreement with the Canal and River Trust for expenditure of
up to £0.643 million from the West Yorkshire plus Transport
Fund.
(iv) That
the Combined Authority enters into an addendum to the existing
funding letter with Kirklees Council for expenditure of up to
£0.728 million from the Active Travel Fund.
(v) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.