Issue - decisions

CityConnect Phase 3 Canals - Leeds Liverpool Shipley

29/07/2021 - CityConnect Phase 3 Canals - Leeds Liverpool Shipley

Resolved: That in respect of the CityConnect Phase 3 Canals - Leeds Liverpool Shipley, the Combined Authority approves, subject to the conditions set by PAT stated in the submitted report:

(i)       That the CityConnect Phase 3 Canals - Leeds Liverpool Shipley scheme proceeds through decision point 4 (full business case) and work commences on activity 5 (Delivery).

(ii)      That approval to the Combined Authority’s contribution of £1.981 million which will be funded from West Yorkshire plus Transport Fund (£1.057 million), Getting Building Fund (£0.500 million) and £0.424 million yet to be secured is given. The total scheme value is £1.981 million.

(iii)      That the Combined Authority enters into an addendum to the existing funding agreement with the Canal and River Trust for expenditure of up to £1.981 million.

(iv)     That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.